top of page
Massey University Sign.jpg

Massey University Buildings

Turitea Campus, Palmerston North, New Zealand

Te Pūtahi-a-Toi, School of Māori Art, Knowledge & Education

Constructed in 1996 for Massey University in Palmerston North, this two-storey building is located in a prominent location on the eastern entrance to the city. Built with a range of materials including precast and insitu concrete, structural steel and reinforced masonry, it features a high standard of finish throughout the building and lighting that has seen it become a landmark for passing motorists.

__________________________________________________________________

 

Our Role

Jason Hatcher was a senior draftsman, developing working design and construction drawings with the architect.

Location

Massey University, Turitea Campus

Palmerston North, New Zealand

Owner

 

Massey University

Contractor

McMillan and Lockwood Ltd

Designer

Ormond Stock Associates (Structural Engineer)

Royal Associates (Architect)

Total Contract Value

NZ$3 million

Timeline

1996

Construction Method

Precast reinforced concrete tilt slab walls with reinforced concrete block walls and structural steel framing on concrete slab floor

Science Towers C & D Additional Floors

Massey University science towers are a group of four buildings. Science towers A, B & C were built from 1967 to 1969, and science tower D was built from 1981 to 1982. The buildings were all constructed from cast-in-place concrete columns, beams and floor slabs. All four towers were four stories high.

By the early 1990's, more space was needed for offices and laboratories, and it was decided the existing building structures could support the construction of a fifth floor. The additions would be made to towers C and D only. The existing concrete roof slab would have a level topping slab applied, and a lightweight structural steel framing system would be added to enclose the new laboratories and offices on the fifth floor.

__________________________________________________________________

 

Our Role

Jason Hatcher was the sole senior draftsman, working with the architect to develop working design and construction drawings. The existing design and construction drawings were available to assist in determining the existing building structure.

Location

Massey University, Turitea Campus

Palmerston North, New Zealand

Owner

 

Massey University

Contractor

Designer

Ormond Stock Associates (Structural Engineer)

Total Contract Value

NZ$ 2 million - Tower C

NZ$ 2 million - Tower D

Timeline

1993 - Tower C

1995 - Tower D

Construction Method

Structural steel framing on the top of an existing reinforced concrete building structure

Landcare Research Building

This building is a three level building with offices and laboratories. The structure is made up of precast and cast-in-place reinforced concrete columns and floor slabs with reinforced concrete floor slabs.

__________________________________________________________________

 

Our Role

Jason Hatcher was sole draftsman detailing the design and construction drawings. Jason was also the liaison between the structural engineer and contractor.

Location

Massey University, Turitea Campus

Palmerston North, New Zealand

Owner

 

Massey University

Contractor

Designer

Ormond Stock Associates (Structural Engineer)

Total Contract Value

NZ$1.5 million

Timeline

1994

Construction Method

Precast and cast-in-place reinforced concrete columns and floor beams with composite reinforced concrete floor slabs in a multi-story building

Centre for University Extramural Studies

This building is a two level building with offices and laboratories. The structure is made up of precast and cast-in-place reinforced concrete columns and floor slabs with reinforced concrete floor slabs.

__________________________________________________________________

 

Our Role

Jason Hatcher detailed the building structure design and construction drawings by hand.

Location

 

Massey University, Turitea Campus

Palmerston North, New Zealand

Owner

 

Massey University

Contractor

Designer

Ormond Stock Associates (Structural Engineer)

Total Contract Value

NZ$1.2 million

Timeline

1993

Construction Method

Precast and cast-in-place reinforced concrete columns and floor beams with composite reinforced concrete floor slabs in a multi-story building

bottom of page